Which of the following statements is / are incorrect? Choose all that apply. A Applying at least one constraint to every task ensures that all

Which of the following statements is/are incorrect? Choose all that apply.
A Applying at least one constraint to every task ensures that all tasks in a project schedule progress smoothly.
B
The As Soon As Possible task constraint is the defaul for tasks scheduled from the project finish date
C
It's best to use a date constraint only when starting or finishing a task by a specific time is required for task completion or project outcome.
D
Setting a task date constraint increases the complexity of your project schedule and reduces the flexibility of scheduling options.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students also viewed these General Management questions