Which of the following statements is CORRECT? You need to spend a sunk cost to make the project feasible A sunk cost is a cost
Which of the following statements is CORRECT?
You need to spend a sunk cost to make the project feasible
A sunk cost is a cost that can be refunded if you reject the project
A sunk cost is money spent that cannot be avoided even if you reject the project
You must always include sunk cost into your NPV analysis since it has been spent
You can exclude sunk cost in an IRR calculation but not in an NPV calculation