Which of the following statements is true? a To calculate the early start date of an activity, you add 1 to the early finish date

Which of the following statements is true? a To calculate the early start date of an activity, you add 1 to the early finish date of the previous activity. b If an activity on a network diagram has two predecessor activities, the early start date of any successor activity is the smallest early finish date of the predecessor activities. c To calculate the critical path in a network diagram, you have to compare the early start date of an activity to its early finish date. d If a project schedule changes, the network diagram's critical path will also change

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Hospitality Law

Authors: Jack P Jefferies, Banks Brown

5th Edition

0866123458, 9780866123457

More Books

Students also viewed these General Management questions

Question

14. Now reconcile what you answered to problem 15 with problem 13.

Answered: 1 week ago