Which of the following statements regarding critical paths is true? a. The duration of the critical path is the average duration of all paths in
Which of the following statements regarding critical paths is true?
a. The duration of the critical path is the average duration of all paths in the project network.
b. Some activities on the critical path may have slack
c. On a specific project, there can be multiple critical paths, all with exactly the same duration
d. The shortest of all paths through the network is the critical path
e. Every network has exactly one critical path