Which of these are false? An activity has an early start (ES) of day 3, a late start (LS) of day 13, and early finish
Which of these are false? An activity has an early start (ES) of day 3, a late start (LS) of day 13, and early finish (EF) of day 9, and late finish (LF) of day 19. The activity: Has a lead Has a lag Is not on the critical path Is progressing well Is on the critical path