Which one of the following must be determined for government property to be furnished to a contractor?
Fantastic news! We've Found the answer you've been seeking!
Question:
Which one of the following must be determined for government property to be furnished to a contractor?
It is clearly demonstrated to be in the contractor's best interest.
The contractor claims an inability or unwillingness to supply its own resources, and the government has that property available.
Providing the property does not substantially increase the government's risk.
The overall benefit to the procurement exceeds the increased cost of administration, excluding disposal costs.