Which one of the following statements is true about the Project Evaluation and Review Technique ( PERT ) ? a . Pert uses discrete duration
Which one of the following statements is true about the Project Evaluation and Review Technique PERT
a
Pert uses discrete duration time estimates.
b
Using the PERT weighted average for activity duration estimates removes the risk of uncertainty in activity estimates.
c
PERT applies the critical path method to a weighted average duration estimate.
d
The application of PERT requires the assumption of a bell curve for activity duration estimates