Which one of the following statements is true about the Project Evaluation and Review Technique ( PERT ) ? a . Pert uses discrete duration

Which one of the following statements is true about the Project Evaluation and Review Technique (PERT)?
a.
Pert uses discrete duration time estimates.
b.
Using the PERT weighted average for activity duration estimates removes the risk of uncertainty in activity estimates.
c.
PERT applies the critical path method to a weighted average duration estimate.
d.
The application of PERT requires the assumption of a bell curve for activity duration estimates

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Early Entrepreneurship Everything You Need To Start Early

Authors: Dhruvv Lohia

1st Edition

979-8889759683

More Books

Students also viewed these General Management questions