which rough-cut capacity technique determines future labor or machine requirements by work center using data that is easily acquired but is only accurate if the
which rough-cut capacity technique determines future labor or machine requirements by work center using data that is easily acquired but is only accurate if the inputs are accurate and the work center routings do not change?A project has four paths. Path 1 has a duration of 2 weeks, Path 2 has a duration of 5 weeks, Path 3 has a duration of 8 weeks, and Path 4 has a duration of 11 weeks. What the duration of the project? 2 weeks 5 weeks 11 weeks 8 weeks