Which TWO of the following is a probable causes of an adverse labor efficiency variance? A. The original budgeted hours were set too low. B.
Which TWO of the following is a probable causes of an adverse labor efficiency variance?
A. The original budgeted hours were set too low.
B. The employees were more skilled than had been planned for.
C. Sales units were lower than budgeted.
D. A lower quality of material was used.