While doing earned value calculations, one should calculate the two important indicators to make comments on the project's cost and schedule performances. What are these
While doing earned value calculations, one should calculate the two important indicators to make comments on the project's cost and schedule performances. What are these two indicators? Question 49 options: PV (Planned Value) and AC (Actual Cost) SPI (Schedule Progress Index) and CPI (Cost Progress Index) PV (Planning Value) and AC (Accounted Cost) SPI (Schedule Performance Index) and CPI (Cost Performance Index)