While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger
While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk? Review the results with the project manager afterward Use the mean answers provided by the project team Remind the project team to keep an open mind Review published operational experience reports