While planning a project, Jane notices that the planned expenditures have exceeded the project's funding limits. What should be the next best thing to do?
While planning a project, Jane notices that the planned expenditures have exceeded the project's funding limits. What should be the next best thing to do? A. Eliminate some work to level out expenditures B. Reschedule work to level out the rate of expenditures C. Increase the funding limits D. Take care of it during execution