While reviewing uour project resource histogram you notice several peaks and valleys as resources are not evenly distributed in your project . In order to
While reviewing uour project resource histogram you notice several peaks and valleys as resources are not evenly distributed in your project . In order to evenly utilize resources as much as possible . You decide to move some. Activities from week when you using a lot of resources to the week when you hardly using . Which techniques are you using in this case? A resource levelling b overtime c schedule compression d schedule control