While trying to determine the schedule for the project, the project manager has been informed from the team that each line of code will take
While trying to determine the schedule for the project, the project manager has been informed from the team that each line of code will take about 15-45 minutes to write and debug. Their will about 1 million lines of code in the application. What schedule estimating technique best describes this estimate