While working on a multinational project, the project manager has decided to represent the project budget in American dollars, even though the project will span
While working on a multinational project, the project manager has decided to represent the project budget in American dollars, even though the project will span nine different countries. This will make the budget uniform and easier for the stakeholders to understand. Where will the project manager document the units of measurement for the budget? a Project document b Cost management plan c Funding management plan d Basis of estimate