White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The

White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates:

Department
Cutting Finishing
Direct labor-hours 9,000 77,000
Machine-hours 50,300 3,700
Total fixed manufacturing overhead cost $ 380,000 $ 538,000
Variable manufacturing overhead per machine-hour $ 3.00
Variable manufacturing overhead per direct labor-hour $ 3.75

Required:

1. Compute the predetermined overhead rate for each department.

2. The job cost sheet for Job 203, which was started and completed during the year, showed the following:

Department
Cutting Finishing
Direct labor-hours 5 12
Machine-hours 84 3
Direct materials $ 750 $ 370
Direct labor cost $ 110 $ 264

Using the predetermined overhead rates that you computed in requirement (1), compute the total manufacturing cost assigned to Job 203.

3. Would you expect substantially different amounts of overhead cost to be assigned to some jobs if the company used a plantwide predetermined overhead rate based on direct labor-hours, rather than using departmental rates?

Compute the predetermined overhead rate for each department. (Round your answers to 2 decimal places.)

Department
Cutting Finishing
Predetermined overhead rate per MH per DLH
  • Using the predetermined overhead rates that you computed in requirement (1), compute the total manufacturing cost assigned to Job 203. (Round intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.)
  • Would you expect substantially different amounts of overhead cost to be assigned to some jobs if the company used a plantwide predetermined overhead rate based on direct labor-hours, rather than using departmental rates?

    Using the predetermined overhead rates that you computed in requirement (1), compute the total manufacturing cost assigned to Job 203. (Round intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.)

    Total manufacturing cost
  • Yesradio button unchecked1 of 2
    No

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Theodore Christensen, David Cottrell, Cassy Budd

13th Edition

1260772136, 9781260772135

More Books

Students also viewed these Accounting questions