Who is responsible for determining what tasks have to be done in a matrix project management structure? A. The functional manager B. The low level
Who is responsible for determining what tasks have to be done in a matrix project management structure? A. The functional manager B. The low level management C. Both are responsible D. The project manager E. This is no pattern of who takes responsibility F. None of these are true