Why is slack time valuable information for project managers? Multiple choice question. All activity slack times are added up to determine the critical path slack
Why is slack time valuable information for project managers? Multiple choice question. All activity slack times are added up to determine the critical path slack time Resources may be shifted to more critical activities away from those with slack The workers on the slack activities may not be hired back due to slow efforts