will you please explain step by step how to solve this problem? i know the answers are there already i just need to undertand how
will you please explain step by step how to solve this problem? i know the answers are there already i just need to undertand how to do it for the future. thanks :)
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 16. a) The probability that the project will be completed in 8 months = (round your response to four decimal places). b) The probability that the project will be completed in 23 months = (round your responso to four decimal places). c) The probability that the project will be completed in 28 months m (round your response to four decimal places). d) The probability that the project will be comploted in 40 months = (round your response fo four decimal places). e) The due date that yields a 95% chance of completion = months (round your response to two decimal places) Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started