Question

1 Approved Answer

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 54 units. The process time for each step is as follows:

Process Step 1 6 minutes
Process Step 2 9 minutes
Process Step 3 4 minutes
Process Step 4 8 minutes

The time required to move each batch between steps is 16 minutes. In addition, the time to move raw materials to Process Step 1 is also 16 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 16 minutes.

The new lean layout will allow the company to reduce the batch sizes from 54 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 3 minutes. The processing time in each step will stay the same.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and proposed production approaches. If required, round percentages to one decimal place.

Present Approach Proposed Approach
Value-added time min min
Non-value-added time min min
Total lead time min min
Value-added ratio (as a percent) % %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Assurance And Risk

Authors: W. Robert Knechel, Steve Salterio, Brian Ballou

2rd Edition

0324022131, 978-0324022131

More Books

Students also viewed these Accounting questions

Question

What is the purpose of a labor and materials payment bond?

Answered: 1 week ago

Question

Describe alternative paid time off policies.

Answered: 1 week ago

Question

Describe customized benefit plans.

Answered: 1 week ago