Question

1 Approved Answer

Williamston Widgets Inc. (WWI) wishes to determine whether it would be advisable to replace an existing production system with a new automated one. They have

Williamston Widgets Inc. (WWI) wishes to determine whether it would be advisable to replace an existing production system with a new automated one. They have hired you as a consultant to determine whether the new system should be purchased. The data you will need is as follows:

  • WWI has decided to set a project timeline of 4 years.
  • The new system will cost $3,200,000. It will be depreciated (straight line) over a five-year period (its estimated useful life), assuming a salvage value of $200,000 the amount the company will be writing the new system down to over its five-year expected life).
  • The old system, which has been fully depreciated, could be sold today for $506,329. The company has received a firm offer for the system from Stockbridge Sprockets, and WWI will sell it only if they purchase the new system.

  • Additional sales generated by the superior products made by the new system would be $3,000,000 in Year 1. In Years 2 and 3 sales are projected to grow by 4.5% per year. However, in Year 4 sales are expected to decline by 10% per year as the market starts to become saturated.

  • Total expenses have been estimated at 74.0% of Sales.

  • The firms tax rate 21%.

  • WWI requires a minimum return on the replacement decision of 8.5%.

  • A representative from Stockbridge Sprockets has told WWI that they will also buy the system from them at the end of the project (the end of Year 4) for $600,000. WWI has decided to include this in the terminal value of the project.

  • The project will require $200,000 in additional Net Working Capital, 40% of which will be recovered at the end of the project.

Part 2: Alternate Scenario 1:

A consultant has told the company that perhaps their sales growth expectations are a bit too high, and that they might have underestimated expenses. Assume that expenses as a percentage of sales will be 74.5% instead of 74.0% and that sales growth in Years 2 and 3 will be 4.3% instead of 4.5% (all other estimates remain the same). Recalculate NPV and IRR.

image text in transcribed

Part 3: Alternate Scenario 2:

Reverting back to the Base Case estimates and assumptions, now assume that sales growth in Years 2 and 3 will be 5.0% each year instead of 4.5% (all other estimates remain the same).

image text in transcribed

Part 4: Alternate Scenario 3:

Revert back to the Base Case estimates and assumptions. Assume sales growth in Years 2 & 3 will be 4.3% instead of 4.5%, sales in Year 4 will only decline by 5% instead of 10%, and expenses as a percentage of sales will be 74.8% instead of 74.0% (all other estimates remain the same). Recalculate NPV and IRR.

image text in transcribedimage text in transcribed

Part 5: Making a decision:

WWI has hired a consultant to look over all of their estimates, assumptions, and calculations. The consultant believes the company was too optimistic with their base case scenario, but concluded that the company did an adequate job of accounting for the most likely alternate scenarios. The have estimated the probability of each occurring:

Base case: 45%

Alternate Scenario 1: 30%

Alternate Scenario 2: 5%

Alternate Scenario 3: 20%

Using the above data, make a decision as to whether you will recommend to WWI whether the accept or reject this project.

image text in transcribed

For Alternate Scenario 1, is the Net Present Value positive or negative? Multiple Choice Positive Negative For Alternate Scenario 2, is the Net Present Value positive or negative? Multiple Choice Positive Negative For Alternate Scenario 3, is the Net Present Value positive or negative? Multiple Choice Positive Negative Based on your overall analysis, should the company Accept of Reject this project? Multiple Choice Accept Reject BONUS QUESTION: What is the weighted NPV of the entire project? Numeric Response For Alternate Scenario 1, is the Net Present Value positive or negative? Multiple Choice Positive Negative For Alternate Scenario 2, is the Net Present Value positive or negative? Multiple Choice Positive Negative For Alternate Scenario 3, is the Net Present Value positive or negative? Multiple Choice Positive Negative Based on your overall analysis, should the company Accept of Reject this project? Multiple Choice Accept Reject BONUS QUESTION: What is the weighted NPV of the entire project? Numeric Response

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions