Question
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights.
Windhoek Mines, Ltd., of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area: |
Cost of new equipment and timbers | $ | 400,000 |
Working capital required | $ | 130,000 |
Annual net cash receipts | $ | 145,000* |
Cost to construct new roads in three years | $ | 46,000 |
Salvage value of equipment in four years | $ | 71,000 |
|
*Receipts from sales of ore, less out-of-pocket costs for salaries, utilities, insurance, and so forth. |
The mineral deposit would be exhausted after four years of mining. At that point, the working capital would be released for reinvestment elsewhere. The companys required rate of return is 18%. |
Click here to view Exhibit 11B-1 and Exhibit 11B-2, to determine the appropriate discount factor(s) using tables. |
Required: | |
a. | Determine the net present value of the proposed mining project. (Any cash outflows should be indicated by a minus sign. Use the appropriate table to determine the discount factor(s).) |
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started