Question

1 Approved Answer

Windsor Construction Company has entered into a contract beginning January 1 , 2 0 2 0 , to build a parking complex. It has been

Windsor Construction Company has entered into a contract beginning January 1,2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period.
202020212022
Costs to date $260,580 $446,620 $618,000
Estimated costs to complete $345,420 $139,380 $0
Progress billings to date $272,000 $551,000 $891,000
Cash collected to date 242,000501,000891,000
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.
Gross profit recognized in 2020 $
Gross profit recognized in 2021 $
Gross profit recognized in 2022 $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: John Hoggett, Lew Edwards, Evelyn Hogg, John Medlin, Matthew Tilling

8th Edition

1742466362, 978-1742466361

More Books

Students also viewed these Accounting questions

Question

3.1 Given A = 3E1, E3, E6, E94 , define A.

Answered: 1 week ago