Question
Winkeywants to get an update from her project manager on one of her flower shop expansions. The earned value table for the project appears below.
Winkeywants to get an update from her project manager on one of her flower shop expansions. The earned value table for the project appears below. Determine the status of the project (calculate PV, EV, AC, CPI, SPI, Cost to Completion and Time to Completion) throughJune (after 6 months)and comment on this 7 month project. (10 marks)
Activity | Jan | Feb | Mar | Apr | May | Jun | Jul | Plan | % Complete | Earned Value |
Grading | 500 | 150 | 650 | 100% | ||||||
Footings | 150 | 150 | 300 | 100% | ||||||
Foundation | 1000 | 300 | 1,300 | 75% | ||||||
Masonry | 300 | 300 | 200 | 800 | 60% | |||||
Interior | 900 | 2,000 | 2,900 | 45% | ||||||
Cabinet Install | 1,000 | 400 | 1400 | 20% | ||||||
Painting | 350 | 400 | 750 | 10% | ||||||
Monthly Plan | 500 | 300 | 1150 | 600 | 1,200 | 3,550 | 800 | |||
Cumulative | ||||||||||
Monthly Actual | 600 | 400 | 700 | 800 | 800 | 2,800 | 0 | |||
Cumulative Actual |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started