Winona Manufacturing operates two-eight hour shifts per day. Downtime for lunches, breaks and equipment set-ups equals a total of 1.50 hours for the 24 hour
Winona Manufacturing operates two-eight hour shifts per day. Downtime for lunches, breaks and equipment set-ups equals a total of 1.50 hours for the 24 hour operating day. Annual customer demand is 69,310 units and Winona Manufacturing operates 239 days per year. What is Winonas takt time in seconds.
A. 290
B. 180
C. 870
D. 522
Dez Inc. has successfully implemented lean manufacturing practices. Based on current demand Dezs takt time is 200 seconds and cycle time is 3,200 seconds. Dez operates two-eight hour shifts, 240 days per year.
How many workers are needed for Dezs current production process and current demand?
A.
125
B.
16
C.
3,200
D.
13
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started