Within the Bill of Quantities an item of escavation has not been divided into different depth classifications, which the method of measurement requires. The Contractor
Within the Bill of Quantities an item of escavation has not been divided into different depth classifications, which the method of measurement requires.
The Contractor notifies a compensation event under clause 61.3. Is this correct? How should the PM respond and within what timescale?