Question

1 Approved Answer

Wizard has contracted with Ace Engineering Pty Ltd (Ace) to build the tracks of a new levitating ghost train ride. The building to house the

Wizard has contracted with Ace Engineering Pty Ltd (Ace) to build the tracks of a new levitating ghost train ride. The building to house the tracks has already been built. The contract was validly formed on 1 July 2021 and contains the following provisions:

Clause 1: Ace will build 100 metres of track made of neodymium magnetic alloy, following the course set out in the Ghost Train Specifications that have been provided by Wizard. Clause 2: Ace must provide weekly progress reports to Wizard. Clause 3: The contract price will be $500 000, with Wizard to pay $100 000 upfront as a deposit. Clause 4: Testing of the tracks is to commence on 1 November 2021. Clause 5: The tracks must be fully operational by 1 December 2021. Time is of the essence

The contract was signed by both parties and Wizard paid Ace $100 000. Ace commenced building the track. After Ace had built 95 m of track there was a fire at the worlds largest neodymium mine and the global price rose ten-fold. Ace is refusing to complete the last 5 metres of track. Required: i) Analyse how each term is to be characterised. (3 marks) ii) Ace told Wizard this track is as good as done and is demanding to be paid the outstanding $400 000. Wizard told Ace the contract is frustrated, we owe you nothing. Does Wizard have to pay Ace anything? If so, how much? (12 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions