Question

1 Approved Answer

Wollongong City is considering the construction of a new waste treatment plant. Land acquisition will cost $120,000. The construction works required for the plant will

Wollongong City is considering the construction of a new waste treatment plant. Land acquisition will cost $120,000. The construction works required for the plant will cost $600,000. Environmental inspection and other expenses will cost $60,000. The plant will be built in Year 0 and will become fully operational in Year 1 for six years (i.e. until Year 6). The annual operating cost for the plant is estimated to be fixed at $120,000 during its anticipated 6-year service life. This waste treatment plant is expected to reduce $12 in the average annual waste treatment fee for each of the 35,000 households that it will serve. The reduction in the annual waste treatment fee and the number of households in Wollongong City are both assumed to be fixed for the 6 years. Changes in the environmental conditions (air pollution and contamination to surrounding lands) must be reflected at the cost of $150,000 at the end of the service life of the plant.

Determine the Internal Rate of Return (IRR) of the project, given that the IRR is between 25% and 30%. (4 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Montgomerys Auditing Classic Reprint Series

Authors: Robert Hiester Montgomery

1st Edition

1390439356, 978-1390439359

More Books

Students also viewed these Accounting questions