Work center A produces parts that are then processed by work center B . Kanban containers used by the work centers hold 1 1 0

Work center A produces parts that are then processed by work center B. Kanban containers used by the work centers hold 110 parts. The overall rate of demand is 3.5 parts per minute at work center B. The table below shows setup, run, move, and wait times for parts at each of the work centers.
What is the minimum number of containers needed between these two work centers?
Two work centres namely A, and B.
Setup time for A =3
Setup time for B =4
Run time (per part) for A =0.2
Run time (per part) for B =0.3
Move time for A =3
Move time for B =5
Wait time for A =15
Wait time for B =5
Overall rate of Demand (D)=3.5
Containers used by the work centres hold parts (C)=110

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions