Question

1 Approved Answer

World Company expects to operate at 70% of its productive capacity of 23,000 units per month. At this planned level, the company expects to use

World Company expects to operate at 70% of its productive capacity of 23,000 units per month. At this planned level, the company expects to use 12,075 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.750 direct labor hours per unit. At the 70% capacity level, the total budgeted cost includes $48,300 fixed overhead cost and $144,900 variable overhead cost. In the current month, the company incurred $197,750 actual overhead and 11,625 actual labor hours while producing 13,900 units. (Do not round intermediate calculations. Round "OH costs per DL hour" to 2 decimal places.)

(1) Compute the predetermined standard overhead rate for total overhead.
Predetermined OH rate
Variable overhead costs
Fixed overhead costs
Total overhead costs
(2) Compute the total overhead variance.
--------Actual production 13,900 units --------
Standard DL Hours Overhead costs applied Actual results Variance Fav./Unf.
Variable overhead costs
Fixed overhead costs
Total overhead costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The TL 9000 Guide For Auditors

Authors: Mark Kempf

1st Edition

087389510X, 978-0873895101

More Books

Students also viewed these Accounting questions