World Company expects to operate at 80% of its productive capacity of 56.250 units per month. At this planned level, the company expects to use 27.900 standard hours of direct labor Overhead is allocated to products using a predetermined standard rate of 0.620 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $64,170 fixed overhead cost and $315.270 variable overhead cost. In the current month, the company incurred $340,000 actual overhead and 24.900 actual labor hours while producing 38,000 units. (1) Compute the overhead volume variance Classify each as favorable or unfavorable. (2) Compute the overhead controllable variance. Classify each as favorable or unfavorable Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the overhead volume variance Classify as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance. Round OH costs per DL hour" to 2 decimal places.) Fixed Overhead Applied Fixed overhead applied Volume Valance Volume vanance Required 2 > World Company expects to operate at 80% of its productive capacity of 56,250 units per month. At this planned level, the company expects to use 27.900 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.620 direct labor hour per unit. At the 80% capacity level, the total budgeted cost includes $64,170 fixed overhead cost and $315,270 variable overhead cost. In the current month, the company incurred $340,000 actual overhead and 24,900 actual labor hours while producing 38,000 units. (1) Compute the overhead volume variance Classify each as favorable or unfavorable (2) Compute the overhead controllable variance Classify each as favorable or unfavorable. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the overhead controllable variance. Classify each as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.) Total actual overhead Flexible budget overhead Total Overhead controllable variance