Question
WP Budget Technique Actual Start Actual Finish MAR APR MAY 1.2.2.1$10,000Fixed Formula (50/50)15 MAR15 APR 1.2.2.2$20,000Percent Complete01 APR21 APR 1.2.2.3$16,000Fixed Formula (0/100)15 MAR15 MAY Monthly
WPBudgetTechniqueActual StartActual FinishMARAPRMAY1.2.2.1$10,000Fixed Formula (50/50)15 MAR15 APR 1.2.2.2$20,000Percent Complete01 APR21 APR 1.2.2.3$16,000Fixed Formula (0/100)15 MAR15 MAY Monthly Earned Value???Cumulative Earned Value
Figure 1. Earned Value Metrics for Work Packages 1.2.2.1, 1.2.2.2, 1.2.2.3
Consider the earned value data presented in Figure 1. Based on the information presented, what is the total monthly earned value for the month of April?
a.$5,000 b.$10,000 c.$20,000 d.$25,000Consider the communications model presented in Figure 4. Which element of the model represents what the source hopes to communicate?
a.Encoding b.Message c.Message Channel d.FeedbackConsider the framework for project selection and portfolio management presented in figure 5. During which stage must projects be justified in terms of either organizational survival or growth?
a.Pre-screening stage b.Proposal analysis stage c.Proposal screening stage d.Portfolio selection stage
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started