X Company currently buys a part from a supplier for $13.72 per unit but is considering making the part itself next year. This year, they
X Company currently buys a part from a supplier for $13.72 per unit but is considering making the part itself next year. This year, they purchased 3,100 units of this part; next year, they think they will need 3,400 units. Estimated costs to make the part are:
Per-Unit | Total | ||
Direct materials | $2.96 | $9,176 | |
Direct labor | 4.53 | 14,043 | |
Variable overhead | 3.90 | 12,090 | |
Fixed overhead | 3.40 | 10,540 | |
Total | $14.79 | $45,849 |
Of the estimated fixed overhead, $4,321 are common costs that would be allocated to the part; the rest would be additional fixed overhead costs. X Company currently rents unused factory space for $2,900; it will have to use this space to make the part. If X Company continues to buy the part instead of making it, it will save......
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started