Question

1 Approved Answer

X, Inc., awarded to Y Corp. the development of titsresidentialsubdivisions consisting of 2parcels of land. Liquidated damages was fixed by the parties to serve as

X, Inc., awarded to Y Corp. the development of titsresidentialsubdivisions consisting of 2parcels of land. Liquidated damages was fixed by the parties to serve as penalty in case Y Corp.fails to fulfill the obligation on time.

Notwithstanding three extensions granted by X Corp. to Y Corp., the latter failed to finish the contracted works. It is 94.53% complete. X Corp. wrote Y Corp. advising the latter of its intention to hold Y Corp., liable for liquidated damages (penalty) which it had incurred. Y Corp. claims that its failure to finish the contracted work wasdue toinclement weather. Decide.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ethical Problems In The Practice Of Law Concise Version

Authors: Lisa G. Lerman, Philip G. Schrag

4th Edition

1454891289, 978-1454891284

More Books

Students also viewed these Law questions

Question

How do the events of normal aging affect life satisfaction?

Answered: 1 week ago