X=1, Y=2, Z=6. NOW write down the revised table according to those values. Finally, perform CPM analysis based on the revised table. 1. 15 Find

X=1, Y=2, Z=6. NOW image text in transcribedwrite down the revised table according to those values. Finally, perform CPM analysis based on the revised table.

1. 15 Find the earliest start, earliest finish, latest start and latest finish time using CPM for all of the following activities and also show the critical path: Task T1 T2 T3 T4 T5 T6 17 Duration (days) Dependencies 10 X + 1 T1 Y +1 7 T1, T3 Z +1 T4 3 TN 4 T4, T6 Where, X, Y and Z are 5th, 6th and 7th digit of your student ID, respectively. N=((X+1) % (Z+1) + 1) [% indicates modulus operator, example: (5%2)=1, (2%7)=2] If the value of N >=6, then consider N = 5. N.B.: Make sure you write down your student ID at first and also the values of X, Y, Z and N. Then, write down the revised table according to those values. Finally, perform CPM analysis based on the revised table

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Database Systems

Authors: Ramez Elmasri, Shamkant B. Navathe

7th Edition Global Edition

1292097612, 978-1292097619

More Books

Students also viewed these Databases questions