Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go karts: Deluxe and Basic, Activity Handling materials Inspecting product Processing purchase orders Paying suppliers Insuring the factory Designing packaging Expected costs $690,000 965,000 170,000 240,000 365.000 140,000 Expected Activity 100,000 parts 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. 2. In January of this year, the Deluxe model required 2.500 direct labor hours and the basic model required 6,000 direct labor hours. Assign overhead costs to each model using the single plantwide overhead rate. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. Xle Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go- karts: Deluxe and Basic Activity Expected Costs Expected Activity Handling materiala $690,000 100,000 parts Inspecting product 965,000 1,500 batches Processing purchase orders 170,000 700 orders Paying suppliers 240,000 500 invoices Insuring the factory 365,000 40,000 square feet Designing packaging 140,000 2 models Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours. 2. In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor hours. Assign overhead costs to each model using the single plantwide overhead rate. Complete this question by entering your answers in the tabs below. Required 1 Required 2 In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor hours. Assign overhead costs to each model using the single plantwide overhead rate. (Round "OH cost" answers to 2 decimal places.) Total DL Hours required Plantwide OH Rate Total Overhead Cost Deluxe model Basic model