Question
XYZ company has a project with the following activities, times and precedence relationships. The total production is 900 units per 8 hour shift. a) Draw
XYZ company has a project with the following activities, times and precedence relationships. The total production is 900 units per 8 hour shift.
a) Draw a precedence diagram for the assembly line.
b) Determine the cycle time.
C) Use a station-oriented approach to production line balancing. Determine the loss of balance for each workstation and the degree of imbalance in the system.
D)Use a task-oriented approach to production line balancing. Determine the loss of balance for each workstaton and the degree of imbalance in the system.
E) Indicate some proposal for improvement for both situations, and analyse the results
Time (seconds) Preceding activities Activities 10 --- 5 8 A B C D E F . B, E 17 3 15 10 U I E C, D C F, G, H I J K L 17 12 12 F I K, J Time (seconds) Preceding activities Activities 10 --- 5 8 A B C D E F . B, E 17 3 15 10 U I E C, D C F, G, H I J K L 17 12 12 F I K, JStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started