XYZ Company has started working on their newest project and prepared the following table containing activities, predecessors of activities, and their respective durations. Prepare the
- XYZ Company has started working on their newest project and prepared the following table containing activities, predecessors of activities, and their respective durations. Prepare the PERT chart (diagram) showing all activities and durations for the project based on the information presented in the table.
Activities | Dependent Activity | Activity Time (Weeks) |
A | - | 6 |
B | - | 3 |
C | - | 4 |
D | A | 2 |
E | B | 3 |
F | C | 4 |
G | C | 3 |
H | E, F | 6 |
I | D | 5 |
J | H, G | 3 |
Question
Use the PERT chart to
- work out the critical path.
- identify the critical path activities.
- discuss how the critical path would impact the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started