XYZ Companys manager need your help to evaluate 8 projects, consider the following information to determine the project the manager should be select by Net
XYZ Companys manager need your help to evaluate 8 projects, consider the following information to determine the project the manager should be select by Net present value NPV
Projects | P1 | P2 | P3 |
Cost | 100000 | 150000 | 200000 |
Cash in | 20000 | 25000 | 30000 |
Life )years) | 7 | 9 | 10 |
- Discount rate 14%
- Rearrange the projects if discount rate is 10% and 20%, and find which project you should select in each case.