XYZ Construction Inc. is the general contractor for a fast-food restaurant project. The construction cost is $320,000 and the contract price is $384,00. Please develop

XYZ Construction Inc. is the general contractor for a fast-food restaurant project. The construction cost is $320,000 and the contract price is $384,00. Please develop the cash-flow diagram based on the cash flow information summarized in the table below.

M1 Direct Cost 25,000, Overhead 5,000, Income 0.00,

M2 Direct Cost 55,000, Overhead 5,000, Income 30,000

M3 Direct Cost 80,000, Overhead 5,000, Income 66,000

M4 Direct Cost 60,000, Overhead 5,000, Income 96,000

M5 Direct Cost 30,000, Overhead 5,000, Income 72,000

M6 Direct Cost 40,000, Overhead 5,000, Income 36,000

M7 Direct Cost 0.00, Overhead 0.00, Income 48,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Theory

Authors: Ian Dennis

1st Edition

1138599700, 978-1138599703

More Books

Students also viewed these Accounting questions

Question

What is TCO?

Answered: 1 week ago

Question

Prepare an electronic rsum.

Answered: 1 week ago

Question

Strengthen your personal presence.

Answered: 1 week ago

Question

Identify the steps to follow in preparing an oral presentation.

Answered: 1 week ago