Question
1 Approved Answer
ACTIVITES PREDECESSOR ACTIVITIES A B C D E F G H 1 J K L M N A A B D D D B
ACTIVITES PREDECESSOR ACTIVITIES A B C D E F G H 1 J K L M N A A B D D D B C-E G F-I-J K H-G M TIME FORECAST (DAY) Y 5 1,5 5 X 3 1 4 8 7 5 3,5 6 1 1 1,5 7 6 5 10 10 9,5 5 8 1 2 3 9 6,5 7,5 M 7 5 12 24 13 11 6,5 16 1 3 4,5 11 10 13 TIME (DAY) COST (TURKISH LIRA-TL) NORMAL FAST 1000 1300 500 500 900 1300 2400 2800 1500 2100 1800 2250 1000 1400 1800 2150 50 50 400 400 425 1725 1650 2100 FAST 4 2 4 8 7 6 3 7 1 2 2 8 5 4 According to the table regarding the project activities given above; a) Draw the network diagram for the whole project (AON). b) Calculate the expected time and variances for the activities. c) Determine the earliest completion times of the project. d) Determine the critical path of the project. e) Calculate ES, EF, LS and LF and space times. f) Calculate the probability that the project can be completed in 50 days or less. g) Calculate the probability that the project can be completed in 40 days or more. h) Speed up the project up to 33 days. Calculate the effect on the total project cost. 300 1500 1200 2000
Step by Step Solution
★★★★★
3.57 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Expected time X4YM6 Variance MX62 activities predecessor x y m Te var ES EF LS LF space A 3 5 7 5 044 0 5 0 5 0 B A 1 15 5 2 044 5 7 5 7 0 C A 4 5 12 6 178 5 11 23 29 18 D B 8 10 24 12 711 7 19 7 19 0 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started