XYZ HealthCare, Inc. Case Study In July of 1 9 9 9 , senior management at XYZ recognized that its future growth could very well

XYZ HealthCare, Inc. Case Study
In July of 1999, senior management at XYZ recognized that its future growth could very well be determined by how quickly and how well it implemented project management. For the past several years, line managers had been functioning as project managers while still managing their line groups. The projects came out with the short end of the stick, most often late and over budget, because managers focused on line activities rather than project work. Everyone recognized that project management needed to be an established career path position and that some structured process had to be implemented for project management. A consultant was brought into XYZ to provide initial project management training for 50 out of the 300 employees targeted for eventual project management training. Several of the employees thus trained were then placed on a committee with senior management to design a project management stage-gate model for XYZ.
After two months of meetings, the committee identified the need for three different stage-gate models: one for information systems, one for new products/ services provided, and one for bringing on board new corporate clients. There were several similarities among the three models. However, personal interests
dictated the need for three methodologies, all based upon rigid policies and procedures.
After a year of using three models, the company recognized it had a problem deciding how to assign the right project manager to the right project. Project managers had to be familiar with all three methodologies. The alternative, considered impractical, was to assign only those project managers familiar with that specific methodology. After six months of meetings, the company consolidated the three methodologies into a single methodology, focusing more upon guidelines than on policies and procedures. The entire organization appeared to support the new singular methodology. A consultant was brought in to conduct the first three days of a four-day training program for employees not yet trained in project management. The fourth day was taught by internal personnel with a focus on how to use the
new methodology. The success to failure ratio on projects increased dramatically.
Format
1) Introduction (short introduction of the case, max one slide)
2) Analysis (For Analysis answer the questions stated in this section, Max 10 Slides)
QUESTIONS
1. Why was it so difficult to develop a singular methodology from the start?
2. Why were all three initial methodologies based on policies and procedures?
3. Why do you believe the organization later was willing to accept a singular
methodology?
4. Why was the singular methodology based on guidelines rather than policies
and procedures?
5. Did it make sense to have the fourth day of the training program devoted to the
methodology and immediately attached to the end of the three-day program?
6. Why was the consultant not allowed to teach the methodology?
3) Recommendation/Conclusion (Provide max 2 Slides for recommendation/conclusion)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The ABCs Of Property Management

Authors: Ken McElroy

1st Edition

9781937832537

More Books

Students also viewed these General Management questions

Question

Challenge yourself to look for creative and innovation solutions.

Answered: 1 week ago