XYZ is considering undertaking the pear project, which is a 3-year project with expected cash flows that are not conventional Cash flows are expected to be $29,000 today, $37,000 in 1 year, 552,000 in 2 years, and 547,000 in 3 years. The weighted average cost of capital for XYZ is 4.46 percent. Which one of the following assertions about the net present value (NPV) of the pear project is true? a. Even though the pear project's expected cash flows are not conventional and even though it is possible to compute the NPV of a project with expected cash flows that are not convencional, the NPV of the pear project can not be computed b. The NPV of the pear project equals an amount that is less than or equal to $5.00 C. The NPV of the pear project equals an amount that is greater than $5.00 but less than $5.00 d. The NPV of the pear project equals an amount that is equal to or greater than $5.00 Oe. The NPV of the pear project cannot be computed, because the project's expected cash flows are not conventional and it is impossible to compute the NPV of a project with expected cash flows that are not conventional 5 points Save Answer XYZ is considering undertaking the pear project, which is a 3-year project with expected cash flows that are not conventional. Cash flows are expected to be $29,000 today, $37,000 in 1 year, $52,000 in 2 years, and $47,000 in 3 years. The weighted average cost of capital for XYZ is 4.46 percent. Which one of the following assertions about the net present value (NPV) of the pear project is true? a. Even though the pear project's expected cash flows are not conventional and even though it is possible to compute the NPV of a project with expected cash flows that are not convenzional, the NPV of the pear project can not be computed b. The NPV of the pear project equals an amount that is less than or equal to $5.00 c. The NPV of the pear project equals an amount that is greater than $5.00 but less than $5.00 d. The NPV of the pear project equals an amount that is equal to or greater than $5.00 e. The NPV of the pear project cannot be computed, because the project's expected cash flows are not conventional and it is impossible to compute the NPV of a project with expected cash flows that are not conventional