Question
XYZ Ltd makes 3 products and for the current period there is a shortage of skilled labour with only 10,000 hours available. The selling price
XYZ Ltd makes 3 products and for the current period there is a shortage of skilled labour with only 10,000 hours available. The selling price and cost per unit for each of these products is as follows:
Product X Product Y Product Z
Direct materials 64. 45. 54
Direct labour (paid 7/hour) 56. 49. 70
Selling price 160. 150. 184
Fixed overheads for the period are 50,000. The maximum demand for each product is: Product X 350 Product Y 550 Product Z 480
Required:
Determine the production mix that will maximise profit in the current period and calculate the resulting profit (assume part units can be made).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started