Y7 A project has a forecasted cash flow of $127 in year 1 and $138 in year 2. The interest rate is 6%, the estimated
Y7 A project has a forecasted cash flow of $127 in year 1 and $138 in year 2. The interest rate is 6%, the estimated risk premium on the market is 11.75%, and the project has a beta of 0.67. If you us...