You and the technical team are evaluating the proposal-specific cost estimating relationships (CERs) the contractor used to estimate scrap costs. There are process improvements that
You and the technical team are evaluating the proposal-specific cost estimating relationships (CERs) the contractor used to estimate scrap costs. There are process improvements that could reduce the estimated scrap costs of a key material. Which CER attribute are you and the technical team questioning? Suitability. Correlation. Should cost. Potential misuse