Question

1 Approved Answer

You are a Cost Manager with responsibilility over a set of software development projects. The project effort was planned by the software group, and the

You are a Cost Manager with responsibilility over a set of software development projects. The project effort was planned by the software group, and the total estimated cost generated based on labor rate. There are no assumptions of additional costs to apply (e.g. licenses, supplies, etc.). You receive the status note from the developer outlining project progress, as well as the financial 'actuals' report from the Fianncial mgmt system. You need to generate earned value elements and determine if the project is on budget/schedule.Fill in the Plan/Schedule Status matrix with appropriate values. Generate your Earned Value Report to present to management. Also, answer the following 3 questions:

1) What is the projected ETC? What assumptions did you make, and method did you use, to determine?

2) What is the new EAC?

3) Does this status report warrant a re-plan of the schedule and budget?

WBS / BudgetWBS IDTask DescriptionLabor $sBudgetLaborHoursBudget2161203601.11.21.31.4Intial Requirements Anal

Plan / Schedule /StatusWBS TaskID DescriptionStartDateEndDateEffort Effort Actual Actual Actual(Labor (Labor Start E

Status Report, Submitted June 18

The project is going well, I am pretty much on track, with just a few minor snags along the way. I completed Initial Rqmts Analysis (1.1) on schedule, but was 3 days late starting Allocation (1.2) due to an emergency maintenance task required on production code. I still completed allocation on schedule, however. My Conceptual Design (1.3) was complete early, but because of the dependency on other staff for the design review (1.4), I wasn't able to start Development early (1.5) early. I had to work a few weekends to have the code ready for code review (1.6) starting June 14th. As of today, I still have not received back all review forms that are due, although I don't anticipate any issues. I will begin Int and Test first thing Monday morning.

Labor Hours/$s Actuals Report18-JunTask DescriptionWBS IDLabor $sCharged1.11.21.3LaborHoursCharged2361253542  
 

WBS / Budget WBS ID 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 Task Description Intial Requirements Analysis Requirements Allocation Conceptual Design Design Review Code Development Code Review Integration and Test Release Planning Production Install Hourly Labor Rate: Labor Hours Budget 216 120 360 24 312 40 240 80 16 $45 Labor $'s Budget $9,720 $5,400 $16,200 $1,080 $14,040 $1,800 $10,800 $3,600 $720 $63,360

Step by Step Solution

3.45 Rating (165 Votes )

There are 3 Steps involved in it

Step: 1

PlanSchedule Status Matrix Task Planned Total Estimated Remaining Actuals to Date Variance Task 1 100 50 20 30 Task 2 50 25 20 5 Task 3 75 40 40 0 Ear... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting A Focus on Ethical Decision Making

Authors: Steve Jackson, Roby Sawyers, Greg Jenkins

5th edition

324663854, 978-0324663853

More Books

Students also viewed these Accounting questions

Question

Identify best practices for in-person and online business meetings.

Answered: 1 week ago

Question

Explain the importance of Human Resource Management

Answered: 1 week ago

Question

Discuss the scope of Human Resource Management

Answered: 1 week ago

Question

Discuss the different types of leadership

Answered: 1 week ago

Question

Write a note on Organisation manuals

Answered: 1 week ago