Question
You are a Cost Manager with responsibilility over a set of software development projects. The project effort was planned by the software group, and the
You are a Cost Manager with responsibilility over a set of software development projects. The project effort was planned by the software group, and the total estimated cost generated based on labor rate. There are no assumptions of additional costs to apply (e.g. licenses, supplies, etc.). You receive the status note from the developer outlining project progress, as well as the financial 'actuals' report from the Fianncial mgmt system. You need to generate earned value elements and determine if the project is on budget/schedule.Fill in the Plan/Schedule Status matrix with appropriate values. Generate your Earned Value Report to present to management. Also, answer the following 3 questions:
1) What is the projected ETC? What assumptions did you make, and method did you use, to determine?
2) What is the new EAC?
3) Does this status report warrant a re-plan of the schedule and budget?
Status Report, Submitted June 18
The project is going well, I am pretty much on track, with just a few minor snags along the way. I completed Initial Rqmts Analysis (1.1) on schedule, but was 3 days late starting Allocation (1.2) due to an emergency maintenance task required on production code. I still completed allocation on schedule, however. My Conceptual Design (1.3) was complete early, but because of the dependency on other staff for the design review (1.4), I wasn't able to start Development early (1.5) early. I had to work a few weekends to have the code ready for code review (1.6) starting June 14th. As of today, I still have not received back all review forms that are due, although I don't anticipate any issues. I will begin Int and Test first thing Monday morning.
WBS / Budget WBS ID 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 Task Description Intial Requirements Analysis Requirements Allocation Conceptual Design Design Review Code Development Code Review Integration and Test Release Planning Production Install Hourly Labor Rate: Labor Hours Budget 216 120 360 24 312 40 240 80 16 $45 Labor $'s Budget $9,720 $5,400 $16,200 $1,080 $14,040 $1,800 $10,800 $3,600 $720 $63,360
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
Step: 1
PlanSchedule Status Matrix Task Planned Total Estimated Remaining Actuals to Date Variance Task 1 100 50 20 30 Task 2 50 25 20 5 Task 3 75 40 40 0 Ear...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started