Question

1 Approved Answer

You are a general contractor and an owner requests you perform work that was not within your original scope. The Owner disagrees and refuses to

You are a general contractor and an owner requests you perform work that was not within your original scope. The Owner disagrees and refuses to sign a change order, claiming you are not entitled to any additional compensation or extended completion time. What is likely your best course of action?
Group of answer choices
Perform the work under a reservation of rights and then seek compensation at or near the projects completion.
Pull off the job until the owner comes to its senses and signs the change order.
Terminate the contract, pull off the job, and go find a more reasonable owner to deal with.
Immediately file a lawsuit requesting the Court order the owner to sign the change order.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Of Electronic And Digital Media

Authors: Alan B. Albarran

6th Edition

1305077563, 978-1305077560

More Books

Students also viewed these General Management questions

Question

What is the purpose of the EEOC?

Answered: 1 week ago