You are a project manager, and you are conducting a qualitative risk analysis to prioritize the risks identified in your project. What is the primary
You are a project manager, and you are conducting a qualitative risk analysis to prioritize the risks identified in your project. What is the primary purpose of conducting a qualitative risk analysis? Select one: To determine the cost impact of a risk To determine the schedule impact of a risk To prioritize risks for further analysis or action To determine the likelihood of a risk occurring