You are a project manager for a survey project for child healthcare analysis. You are presenting a project schedule for the project. Which of the
You are a project manager for a survey project for child healthcare analysis. You are presenting a project schedule for the project. Which of the below choices is not a way to display the project schedule?(For Ref Only, Question #: PM-03110) Group of answer choices Probability distribution Bar charts Milestone charts Network Diagram with dates